Signed in as:
filler@godaddy.com
Signed in as:
filler@godaddy.com
The Lovettsville and Neersville areas of North Western Loudoun County as well as neighbouring Frederick County - from the West Virginia line through Gore and Clear Brook, where a new 500kV substation is proposed and on through Clarke County, Virginia and Hampshire and Jefferson County, West Virginia and Frederick County Maryland all now face the possibility of the existing 500kV and 138kV row expanding into a massive transmission infrastructure corridor 550' to 650' wide to accommodate TWO NEW HVAC transmission lines to support the Data Centers in Eastern Loudoun.
These lines will require both expanding the existing easements and new greenfield easements,
If both transmission lines are approved, property owners along the the 15 mile segment through far North Western Loudoun will be devastated by a ROW almost four times as wide as a football field is wide and Eminent Domain takings of about 365 acres in the Lovettsville and Neersville areas alone!
There are no existing transmission corridors anywhere in the PJM region with a 765kV, two 500kV and a 138kV transmission line co-located in the same corridor.
On top of the destruction of 365 acres of private property (acres calculation is for the 200' greenfield easement for the 765kV), our local environment, an unprecedented level of Electromagnetic Fields (EMFs) for the people forced to live beside it, these structures would cut 185' into the skyline and will be the prominent feature of the view shed for the entire area.
If these are approved people in the Lovettsville and Neersville , Gore Clear Brook and Clark County areas will be living beside:
Per the FirstEnergy open house(s) on the 500kV they do not appear to be expanding the easement in the Lovettsville and Neersville area as of 8/12/2025 the poles will be 185' high! Frederick County and Jefferson County have places where the easements are being expanded as well as new greenfield lines around and between the substations. In Clear Crook the proposed Woodside substation would sit 40 feet from existing homes.
The Mid-Atlantic National Interest Electric Transmission Corridor (NIETC) was cancelled by the DOE 12/16/2024 . If any state denies these transmission lines the Federal Government will not have the authority to site the transmission line and the transmission line will not be built!
Underground HVDC Is An Alternative to Overhead HVAC Transmission Lines
The only viable alternative to overhead HVAC transmission lines that would preserve the value of private property, conservation easements, national and state parks faced with the Gore-Doubs-Goose Creek and Valley Link transmission projects would be underground high-voltage direct current (HVDC).
Read more about Underground HVDC here
Help us get the word out by posting our petition on social media!
Download our flyer about these two projects and our proposed HVDC underground alternative and hand it out to your neighbours and friends in Loudoun, Frederick and Clarke counties in Virginia and encourage them to sign our petition!
HVDC underground is applicable to all of the proposed 500kV and 765kV projects in Virginia.
If underground HVDC technology is adapted it will save thousands of private property owners across Virginia form eminent domain easement takings for transmission lines to provide energy for data centers!
Frederick County BOS Meeting
Wednesday, October 8, 7:00 p.m
Board room of the Frederick County administration building,
107 North Kent Street
Winchester, Virginia
I called the Frederick County Board Of Supervisors and spoke with the clerk.
As for the agenda for the 10/8 Meeting:
The planning commission said the application was submitted 9/5 and county has 60 days to act on the application or else it is automatically approved. The next board of supervisors meeting is Wednesday, October 22, 2025 the agenda for that meeting will not be posted until Friday, October 17th .
We need to show up and speak up tomorrow night, the Board Of Supervisors will have time to consider our concerns and must ensure they have an agenda item for a vote to deny or an extension for further review on October 22, 2025.
We want the Board of Supervisors to take a vote that the Woodside substation is not in "substantial accord" and they need to hear from us why it is not . The October 22 Board Of Supervisors meeting is the last meeting before the November 5th deadline we need to impress upon them to build the case for denial now so it can be denied or extend the deadline at the October 22 board meeting.
Please continue to send comments to: osh.ludwig@fcva.us; john.jewell@fcva.us;rwells@fcva.us;bdunn@fcva.us;robert.liero@fcva.us;jslaughter@fcva.us;michael.bollhoefer@fcva.us;jtibbs@fcva.us;ann.phillips@fcva.us
For those of you at the planning commission meeting you will recall one comment by a planning commission member was - we don't have another planning meeting before the deadline (November 5) so lets vote to approve now. We don't want the same situation to play out at the October 22 board of supervisors meeting.
Frederick County BOS Meeting
Wednesday, October 8, 7:00 p.m
Board room of the Frederick County administration building,
107 North Kent Street
Winchester, Virginia
The Planning Commission voted the substation to be in "substantial accord" with the Frederick County Comprehensive Plan, their discussion did not justify their decision. Now their recommendation goes to the Frederick County Board of Supervisors.
The Board of Supervisors has to vote on the Woodside substation "substantial accord" and their vote will OVERRIDE the planning commission's recommendation! We need the Frederick County BOS to vote "NO" and override the Planning Commission's "YES".
Contact the Frederick County BOS NOW and tell them you oppose the Woodside substation because it is not in accordance with the comprehensive plan:
Frederick County BOS emails:
josh.ludwig@fcva.us; john.jewell@fcva.us;rwells@fcva.us;bdunn@fcva.us;robert.liero@fcva.us;jslaughter@fcva.us;michael.bollhoefer@fcva.us;jtibbs@fcva.us;ann.phillips@fcva.us
Make the case for denial for them!
It is not in substantial accord with the comprehensive plan because :
1. The Virginia Code calls for the comprehensive plan to be drafted for the purpose of: “guiding and accomplishing a coordinated, adjusted and harmonious development of the territory which will, in accordance with present and probable future needs and resources, best promote the health, safety, morals, order, convenience, prosperity and general welfare of the inhabitants.”
A substation 40 feet from homes does not meet this criteria.
2. There is no mitigation for current residential properties. Just because in 2023 an area was shaded "blue" for future industrial use in 2035 does not mean a 30 acre substation is in accord with that plan 2 years later! This will gut the home equity of every property in that neighbourhood now! This is not a gradual transmission to industrial use.
3. This substation will take up 70 acres but does not produce jobs. It is an industrial use but it is not an industrial business! And it is not fitting for the character of its surroundings - which is residential, offices , contractors, garages are suitable 500kV substations are not! The only reason NextERA chose this property was because this is the only farmer willing to sell their farm and there are transmission line on the property.
There is no 500kV HVAC Substation in the Frederick County plan - it is not a "feature shown".
There were three Planning Commissioners that voted the Woodside substation was NOT in substantial accord each one had valid reasons for opposing this. Ask Vaughn, Chad and Mollie to Advocate for the community and speak at the Frederick County Board of Supervisors Meeting :
Items 12) Planning Commission Business - Public Hearings and 13) Planning Commission Business - Other Business
At a minimum the Frederick County Board Of Supervisors can extend the deadline for review and engage the Frederick County Attorney to develop a case supporting denial !
Show up to oppose the Woodside substation! Speak Up! Fight !!!!
This is an election year write a letter to the editor, call into a radio talk show, contact a local news show !
Comprehensive plans get reviewed every 5 years - this can be reviewed and overturned figure out who is willing to represent the best interests of residents and who is not and spread the word! Contact every Frederick County Board Of Supervisor and their opponents make this an election issue!
The online comment form is limited to 2000 characters and closes on October 1, 2025 at 12:30 PM
Submit Comments even if you plan on attending in person!
My Comments to the Frederick County Planning Commission:
Frederick County is located between the only base load electric plants with excess capacity and the energy demands of Data Center alley. Clear Brook is already in the cross hairs of not one but TWO massive overhead transmission lines.
The 500kV MARL/Gore-Doubs-GooseCreek line - proposed on new 200' easements in places, re-built in other locations in the existing easement with the existing 138kV in the existing easement on 185' towers.
And the 765kV Valley Link line - a retread of the PATH line defeated in 2012 - only worse! Valley Link is proposed on new 200' easements for its entire length and would be built on V-Structures with guyed-wires.
And NOW in its 2025 Window 1 proposals PJM is ALREADY evaluating a proposal to modify the MARL/Gore-Doubs-GooseCreek project to ADD another 500kV line.
The Woodside substation is NextERA's plan for the property you are currently evaluating for re-zoning:
"Convert the 500kV single circuit 502 Junction - Woodside 500kV project under development (PJM Baseline Upgrade ID b3800.102) to a double circuit configuration between Fort Martin and the NEETMA/APS interconnection point in Frederick County, VA, to accommodate Circuit 1 (b3800.102: 502 Junction – Black Oak – Woodside 500kV) and Circuit 2 (Fort Martin – Sandy Creek – Woodside 500kV)."
Make no mistake, if NextERA prevails and is granted the re-zoning request, NextERA has bought 30+ acres and they will fill it - with industrial infrastructure - to its maximum allowed footprint per the zoning ordinance .
The Clear Brook community as well as other rural towns will be "sandwiched" between multiple overhead HVAC lines , hundred acre data center industrial zones and 10 - 30 acre substations. This is the wrong location for a 30 acre substation. Find a location that is already zoned for industrial use.
Don't Ashburn Clear Brook !
The online comment form is limited to 2000 characters and closes on October 1, 2025 at 12:30 PM
Submit Comments even if you plan on attending in person!
My Comments to the Frederick County Planning Commission:
Frederick County is located between the only base load electric plants with excess capacity and the energy demands of Data Center alley. Clear Brook is already in the cross hairs of not one but TWO massive overhead transmission lines.
The 500kV MARL/Gore-Doubs-GooseCreek line - proposed on new 200' easements in places, re-built in other locations in the existing easement with the existing 138kV in the existing easement on 185' towers.
And the 765kV Valley Link line - a retread of the PATH line defeated in 2012 - only worse! Valley Link is proposed on new 200' easements for its entire length and would be built on V-Structures with guyed-wires.
And NOW in its 2025 Window 1 proposals PJM is ALREADY evaluating a proposal to modify the MARL/Gore-Doubs-GooseCreek project to ADD another 500kV line.
The Woodside substation is NextERA's plan for the property you are currently evaluating for re-zoning:
"Convert the 500kV single circuit 502 Junction - Woodside 500kV project under development (PJM Baseline Upgrade ID b3800.102) to a double circuit configuration between Fort Martin and the NEETMA/APS interconnection point in Frederick County, VA, to accommodate Circuit 1 (b3800.102: 502 Junction – Black Oak – Woodside 500kV) and Circuit 2 (Fort Martin – Sandy Creek – Woodside 500kV)."
Make no mistake, if NextERA prevails and is granted the re-zoning request, NextERA has bought 30+ acres and they will fill it - with industrial infrastructure - to its maximum allowed footprint per the zoning ordinance .
The Clear Brook community as well as other rural towns will be "sandwiched" between multiple overhead HVAC lines , hundred acre data center industrial zones and 10 - 30 acre substations. This is the wrong location for a 30 acre substation. Find a location that is already zoned for industrial use.
Don't Ashburn Clear Brook !
If you miss the data for online submission you can send an email to the members of the Frederick County Board of supervisors (listed below) .
Even if you do submit online comments send the Frederick County BOS an email too! They will be voting on the re -zoning
Frederick County BOS emails:
josh.ludwig@fcva.us; john.jewell@fcva.us;rwells@fcva.us;bdunn@fcva.us;robert.liero@fcva.us;jslaughter@fcva.us;michael.bollhoefer@fcva.us;jtibbs@fcva.us;ann.phillips@fcva.us
Frederick County, Virginia planning commission public hearing on the Woodside Substation Zoning
Wednesday, October 1, 7:30 p.m
The meeting will be held in the board room of the Frederick County administration building,
107 North Kent Street
Winchester, Virginia
The Woodside Station is part of the MARL /Gore-Doubs-Goose Creek project to feed the energy demanded by Loudoun County's data center alley. The property proposed for the substation is close to the existing Stonewall substation in Clear Brook in Frederick County.
This new substation would be located across the street from Joline Drive and the Ridge Way Estates subdivision, this area is zoned residential! Once constructed this will be a magnet for additional transmission lines to serve the data centers in Loudoun County!
Attend in person to have your voice heard and / or submit comments online!
Please be sure to enter comments and be on the record opposing Loudoun County's Electric Infrastructure CPAM land grab.
Direct Testimony on behalf of Loudoun County in the Aspen - Golden Docket: Pg 18 Lines 396 - 403 "The County envisions a pilot program that, in addition to undergrounding all or part of the pilot project under application, would initiate a long-term planning initiative that would include comprehensive plan reform in the participating locality, to identify future transmission corridors and specific criteria for selecting underground projects, which would be favored in all cases. This will create a basis for Planning Staff and the Planning Commission to review applications for substantial accord with the comprehensive plan and applicable zoning, which can stand in place of Certificate of Public Convenience and Necessity review in the SCC."
It bears repeating, given what Loudoun's Planning Commissions have done to Ashburn with the completely unrestrained approval of re-zoning requests for data centers, it's mind-boggling to think people are proposing these same individuals should be allowed to etch-a-sketch transmission lines across private property and approve them and take property by eminent domain to ensure the data centers they approved get the energy they demand.
Comments on the Loudoun County Electrical Infrastructure Plan Amendments will be accepted through the online form (available here) .
Apparently two members of the Loudoun County Planning commission were involved with the sale of a Fauquier County property that has become part of a plan to build a 2.2 million sq.ft data campus in Fauquier County.
According to the article, those members were Ron Meyer and Mark Miller. Mr. Miller bought the property on behalf of JAG MK which is an LLC that Eric Combs (another Loudoun County Planning Commissioner) has been on the board of since 2020. One of the Fauquier County Supervisors also sold his property and naturally its being re-zoned.
"Miller is more than just a minor investor in the project – according to Culbertson, the project would never have materialized if Miller had not connected him to Ron Meyer, the former Loudoun County supervisor who put the Remington Innovation Center application together and pitched it to SDC Capital Partners.
As the application inches through Fauquier County’s review process, Meyer’s Loudoun County perspective is front and center – which he projects as an asset.“I represented Data Center Alley,” Meyer told the Fauquier Times"
Eric Combs was appointed by Michael R. Turner (D-Ashburn) and Supervisor Caleb A. Kerschner appointed Realtor Mark Miller.
Hmmm ....
VA SCC Public Hearings for Comments on the Golden-Mars 500kV Transmission line in Ashburn
Will be held at 6:30 p.m. September 18 at Rock Ridge High School, 43460 Loudoun Reserve Drive, Ashburn, Virginia 20148, arrive 15 minutes early to register to speak
A second hearing will be held 9/29, same place and time.
My understanding is that Loudoun County will be proposing an underground pilot for a portion of the Golden-Mars line, I have not seen the details of the pilot yet.
I support undergrounding ALL transmission lines. The only reason our properties are in peril of being criss-crossed with 500kV and 765kV transmission lines are data center energy demands. These are trillion dollar businesses that can afford to pay to underground ALL lines feeding and encircling Data Center Alley - with whatever technology is feasible underground HVAC or underground HVDC . Data Centers must mitigate the effects of their businesses on residents and private property owners!
No easements should be taken by eminent domain from any private property owner, to host any of these lines. I will make an exception for the data center property owners, because data center are the ones benefiting from the lines. These lines should be located on data center property as much as possible and along highways as far away from private residences as possible.
For both the Haymarket line and the W&O Trail line the local elected representatives took bills to the VA General Assembly defining the pilot program and secured funding for the underground project. The Aspen-Golden and Golden-Mars transmission lines have been in the works for two years now and there has not been a bill passed in the VA General Assembly with a pilot for an underground 500kV line and funding for it.
I asked several elected officials why they are only writing letters to the VA SCC when they can write a bill and have it passed through the VA General Assembly and get funding which would assure the pilot would be built but none of them were able to provide a satisfactory answer.
I did intervene in the Aspen-Golden 500kV case at the Virginia SCC last year and Loudoun County did propose an underground 500kV HVAC alternative. The reference case for the underground 500kV HVAC pilot is in Chino Hills California and it is the only reference case for an underground 500kV lines in the entire world - only 3.7 miles of it is underground . Black & Veatch did the engineering for the Chino Hills line.
The pilot Loudoun County proposed for the Aspen-Golden line included a planning component and an approval process using the Comprehensive Plan which would allow Loudoun County to evaluate and approve the siting of the transmission line. This would usurp the power of the VA SCC (The Hearing Examiner required Loudoun County to re-file a "cured" version of the testimony without the "planning component"). The original testimony is still available in the SCC docket. From the pre-filed Direct Testimony of Mr. Giglio on behalf of Loudoun County:
Pg 17 Lines 370 - 373 "Additionally, the pilot program will include a planning component designed to develop protocols to allow the eventual approval of high-voltage underground transmission lines through local planning processes, including substantial accord review and zoning review."
Pg 18 Lines 396 - 403 "The County envisions a pilot program that, in addition to undergrounding all or partof the pilot project under application, would initiate a long-term planning initiative that would include comprehensive plan reform in the participating locality, to identify future transmission corridors and specific criteria for selecting underground projects, which would be favored in all cases. This will create a basis for Planning Staff and the Planning Commission to review applications for substantial accord with the comprehensive plan and applicable zoning, which can stand in place of Certificate of Public Convenience and Necessity review in the SCC."
It remains to be seen what Loudoun County is proposing for this pilot. However, I can state with assurance I will adamantly oppose ANY pilot that contains a "planning component" where Loudoun County Planning Staff and Planning Commission work with electric utilities to site and evaluate and approve the transmission line in standard accord with the comprehensive plan.
The VA State SCC is the only entity with the constitutional authority to evaluate and site transmission lines and issue a certificate that results in the taking of private property for transmission easements.
Given what Loudoun's Planning Commissions have done to Ashburn with the completely unrestrained approval of re-zoning requests for data centers, it's mind-boggling to think people are proposing these same individuals should be allowed to etch-a-sketch transmission lines across private property and approve them and take property by eminent domain to ensure the data centers they approved get the energy they demand.
The proposals to solve the latest projected set of problems caused by the data center demand in Loudoun County's data center alley are to be discussed at the September 9th, PJM TEAC at 10:30 am - 12:30 am
Proposal 20225 - W1 - 896 proposes to add a second 500kV transmission line on to NextERA's MARL transmission line (the current single 500kV circuit would be come a a double circuit 500kV) from the Ft. Martin generation plant to a new substation north of Bruceton Mills and on to Gore, Virginia. From Gore through Frederick County, VA to the currently proposed Woodside station, a new 200' easement would be taken along the side of FirstEnergy's Gore-Doubs-Goose Creek line for another 500kV transmission line.
This would bring the width of the row up to 600' in West VA - the existing 500kV, a double circuit 500kV (MARL+) and the 765kV Valley Link for a total of 2265kV!
In Frederick County, VA there would be the existing 500kV, the Gore-Doubs-Goose Creek 500kv + 138kV the Valley Link 765kV PLUS a new 500kV in a new 200' easement bringing the width of the easement up to 800' to support a total of 2403kV!
PJM will be evaluating this proposal among others in the next several TEAC meetings and will make a decision on which to approve towards the end of the year.
Petitions to update the Black & Veatch Study and have one HVDC underground solution for both lines coming soon!
First Energy filed a Notice of Intent to file an application for the Gore-Doubs-Goose Creek transmission line through Jefferson County, WV at the West Virginia PSC 8/26 !
Next ERA filed a Notice of Intent to file an application for the MARL transmission line through Preston County, Monongalia County, Mineral County and Hampshire County at the West Virginia PSC 8/27!
Both First Energy and NextERA have said the filing was so that a case # could be opened and they intend to file the Application in early December
Gore-Doubs-GooseCreek West VA PSC Docket Number: NOIE Potomac Edison 25C
MARL West VA PSC Docket Number: NOIE NextERA Energy 25A
You don't have to live in West Virginia to submit comments, you can file comments with the PSC for specific dockets.
Submit your comments for West VA PSC NOIE NextERA Energy 25A : here
Submit your comments for West VA PSC NOIE Potomac Edison 25C: here
Submit your comments for both cases NOIE Potomac Edison 25C and NOIE NextERA Energy 25A (submit 2x one for each docket number!)
Submit your comments for both cases NOIE Potomac Edison 25C and NOIE NextERA Energy 25A (submit 2x one for each docket number!)
Make sure to state you are in opposition to MARL and Gore-Doubs-Goose Creek it's the same line!
Per StopPATHWv: "If you are in Jefferson County you may want to start with... has there been sufficient notice and public engagement? Do you feel you have enough details about this project? Did they show you what a 185 ft. tower would look like? Did they give you full details about their construction practices and what to expect?"
West Virginia Code Sec. 24-2-11a(c) says at least 30 business days before the deadline to intervene, the applicant must serve notice by certified mail to all owners of property within the preferred corridor.
You don't need to have a lawyer to intervene at the West VA PSC - in fact once the application has been filed you can intervene pro - se at the start and join with other impacted property owners to have a lawyer represent you all later in the case ! You must intervene to protect your property rights!
PJM is in the midst of another planning cycle and once again the energy demands from Loudoun's Data Center Alley are leading to overloads ... in 2032 so again PJM has requested transmission proposals because because PJM can not order generation. There are multiple proposals one of which double ups on MARL and adds an additional 200' ROW through Frederick County, VA.
Excerpts from the analysis of the proposals by Keryn at the StopPATHWv blog are below:
"One of the proposed projects is numbered 896. This proposal, which may have been made by FirstEnergy or NextEra, calls for turning MARL into a double circuit 500kV transmission line, and adding a second 500kV line to the first segment of GDGC across Frederick County, Virginia."
"The proposed MARL double circuit begins at FirstEnergy's Fort Martin power station in Morgantown, WV. The new 500kV circuit will be added to MARL's proposed towers so that MARL would consist of TWO 500kV transmission lines, possibly hanging from the same new tower. This includes the entire portion of MARL from a point in Mon County to the place in Frederick County, Virginia where the MARL project ends and the Gore-Doubs-Goose Creek project begins. It would impact Mon, Preston, Garrett, Allegany, Mineral and Hampshire Counties. The proposer says it will use "existing right-of-way" but that right-of-way doesn't actually exist yet and will only exist if MARL is approved and built. "
"Once this new double circuit 500kV line gets to the demarcation point between MARL and GDGC in Frederick County, Virginia, it proposes to run on a new 200 foot right of way for 17 miles across Frederick County until it reaches the proposed Woodside substation owned by NextEra. They can't simply continue the double circuit on the same new towers when they get to Frederick County because that is the point where the Gore-Doubs-Goose Creek line is already planned to be constructed as a double circuit with the existing 138kV line. The second 500kV circuit would need a whole new right-of-way parallel to the existing configuration. And don't forget that Valley Link is coming along behind it and creating its own new 200 ft. right-of-way. Frederick County is looking at not only the new 185 ft. tower for the first 500kV circuit, but the addition of two new lines on parallel rights-of-way that would add 400 feet to the existing 250 foot wide corridor. Total if this is selected and completed: 650 feet wide right-of-way with three 500 kV lines, one 138kV line, and one 765kV"
The 500kV MARL /Gore-Doubs-GooseCreek transmission line has an InService Date of 2032, the 765kV Valley Link transmission line has an InService Date of 2029!!
First Energy is already working on siting the 765kV transmission line! I've heard they expect to have open houses in the Fall. We don't know which transmission line they will be submitting an application to the Virginia SCC for first or the order they will be submitting the applications to the other states!.
Please watch this video of the installation of the Wyoming - Jackson Ferry 765kV transmission line and send it to every elected official in Virginia that you know. This is a direct result of the data center policy of the Loudoun County BOS.
Please watch this video of the installation of the Wyoming - Jackson Ferry 765kV transmission line.
These are the same structures as has been proposed for Valley link and is planned to go through Neersville and the Lovettsville area.
This is the only 765kV transmission line built between West Virginia and Virginia and it is the 90 mile Wyoming - Jackson Ferry 765kV transmission line.
The permitting process for that transmission line began in 1991, the final approval and Environmental Impact Statement from the Forest Service was in 2002 and the line was not energised until June of 2006.
Fifteen (15) years for a transmission line that is 1/3 the length of the proposed Valley Link Transmission Line .
Tell FirstEnergy to evaluate the 500kV and the 765kV line and do ONE underground HVDC solution
No one in Western Loudoun should be forced to host an overhead HVAC Infrastructure corridor to plug data centers in Data Center Alley into West Virginia base load generation sources.
Please include in your comments we do not want any more overhead HVAC lines - especially not multiple lines. FirstEnergy has TWO massive infrastructure projects through our area a 500kV and a 765kV. FirstEnergy MUST re-evaluate BOTH of these projects and provide ONE underground HVDC solution. The link below provides fact sheets that can be printed.
Is HVDC underground feasible for the MARL/ Gore-Doubs Goose Creek 500kV and valley link transmission 765kV lines? The short answer is yes! For the PATH 765kV transmission line Black & Veatch did a study that proved HVDC underground was a feasible solution through our area. Although it was more expensive (at that time) . An added benefit is that HVDC lines do not emit EMFs.
• The full title of that study was : Black & Veatch, "PJM Interconnection Potomac-Appalachian Transmission Highline (PATH) Project, HVDC Conceptual Study, B&V Project No.164996, B&V File 42.2004 , FINAL November 17, 2009 This was entered into the record as part of the Virginia SCC Case PUE 2009-00043 Application of PATH Allegheny Virginia Transmission Corporation
• Concept 2 was to use HVDC Underground along the Jefferson County WV through Loudoun County segment of the Mt Storm - Doubs line
• This is the same location PJM has proposed to locate MARL (500kV) and Valley Link (765kV) through Jefferson County, West VA and Loudoun County , VA and into Frederick , MD from Welton Springs to Doubs
• The HVDC with underground Concept 2 (~25 miles underground ) would have cost 2x the overhead HVAC 765kV option ($1, 767M vs $3,595M) The additional $1,828M amounts to an extra $73.12M per mile
• Recent studies by NextGen Highways indicate the price has come down significantly and the installation space is smaller now.
• The Aspen/Golden Underground alternative proposed by Loudoun County to put 3 miles underground would be an additional $480M over the cost of the overhead line. $160M extra per mile!
=> The HVDC underground solution proposed in 2009 costs less per mile that what the county proposed for the Aspen/Golden HVAC underground alternate route
=> Data Center impact fees and taxes can be used fund the additional cost of under grounding Loudoun County must set aside funds for this purpose . At this point many of these companies are worth hundreds of billions to trillions in market caps (Amazon reached a $2 Trillion Stock Value on June 27, 2024 ) . Their executives and boards are paid 100's of billions of dollars . There is more than enough money to cover the cost of using HVDC and undergrounding these lines
=> FirstEnergy is now responsible for two massive transmission lines targeted through our communities (Valley Link and Gore-Doubs-Goose Creek). Its time to re-evaluate and look at ONE single solution - figure out how much power can be reasonable imported from West Virginia and build A SINGLE INCLUSIVE HVDC Underground solution to solve it.
=> PJM TEAC Charts on the concept are attached, the full engineering study (B&V Project No.164996, B&V File 42.2004 , FINAL November 17, 2009) was filed during the Virginia SCC Case PUE 2009-00043 Application of PATH Allegheny Virginia Transmission Corporation
The interactive maps have been posted on first pass it appears that the placement of the poles will be inside FirstEnergy's existing 150' easement with some exceptions. In particular in Jefferson County West, VA around the Millville and Feagan's Mill substations.
Its not possible to tell from the maps how much additional property will be taken to expand the easement to accommodate the 500Kv transmission line to strip trees and vegetation that could interfere with the lines. The existing Dominion 500kV transmission line is in a standard 200' easement.
Rivers Edge has reported that there was a team of workers from Progressive Solutions, hired by Dominion Energy , spraying chemicals in the utility easement! This is on the Lovettsville side they have already sprayed Catoctin View and part way to Rivers Edge our understanding is that they will be continuing down the easement.
If your property has a utility easement they still need to obtain your permission to spray chemicals .
They are also cutting trees, be sure to tell them not to stray outside the existing easement.
DO NOT eat blackberries picked from in the area around the lines!
Comments on the Loudoun County Electrical Infrastructure Plan Amendments will be accepted through the online form (available here) . Letters in opposition to the BOS Plan Amendments can also be sent to bos@loudoun.gov.
*** Note the online form includes the ability to upload documents.
Please write Supervisor Caleb A. Kershner of the Catoctin District directly at caleb.kershner@loudoun.gov And copy Virginia State Delegate Higgins (DelGHiggins@house.virginia.gov) and Virginia State Senator Perry (senatorperry@senate.virginia.gov) whom as I understand it are also supportive of these comprehensive plan changes. If you find out otherwise please let me know and I will correct this and link to their opposition comments to the Loudoun County BOS!
The Loudoun County BOS has no authority to designate transmission corridors for HVAC transmission lines as features in the comprehensive plan nor do they have any authority to guide or direct how high voltage transmission lines are managed in the county. No county in Virginia has been granted this authority! Multiple counties in Virginia abut Loudoun County as do multiple states. The idea that Loudoun County gets to locate transmission corridors is absurd that would imply routes through other Virginia counties and neighbouring states!
Additionally, Loudoun County has no say or sway for under grounding. The driver is cost and the applicable law can be succinctly stated "beneficiary pays". Loudoun County would have to put aside money to pay to have the transmission lines put underground. This could be paid for by Data Center impact fees or Data Center taxes but Loudoun County is not currently putting aside any funds at all and does not have a plan to put aside funding for under-grounding. Loudoun County is in fact looking to decrease the data center taxes.
Our communities (Lovettsville and Between the Hills) "host" the one and only interstate 500kV transmission line in northern Loudoun County.
This would effectively re-zone our properties for data center infrastructure use.
Designating a "transmission corridor" will result in private properties being taken essentially "at will" by utilities sequentially in swaths of 50', 100' and 200' - in perpetuity,for the county's stated purpose of providing power to the data centers.
The county's actions are essentially re-zoning portions of private property as "Data Center Infrastructure" for a transmission build out to support the data center energy expansion in their economic plan.
This is patently unconstitutional and violates private property due process rights prescribed in the Virginia Constitution Section 11. This would create 2 classes of property owners:
- For one set of private property owners Loudoun County will be expending tax payer money to defend those properties from ever having a transmission line
- For the second private property owners Loudoun County will be expendng tax payer money to cause those properties to be taken to support multiple inter-state transmission lines
- The second set of property owners will be financially bankrupt defending their property on successive transmission line cases and ultimately be forced to sell.
Loudoun County is bypassing due process by essentially "reserving" properties in advance for transmission line siting and working behind property owners backs to effectuate the taking by working with utilities in the proposal stage of these projects IN ADVANCE OF APPLICATIONS BEING SUBMITTED TO THE VIRGINIA STATE SCC.
This action is basically teeing up our communities for utility takings negotiated BY Loudoun County BOS to benefit other county private property owners and businesses to our detriment and behind our backs!
Loudoun County BOS is attempting to codify the behind door meetings we are aware they participated in to push the MARL 500kV transmission line into our communities without any notification or consultation with the property owners.
Our Catcotin Elected Officials support these comprehensive plan amendments as do the representatives of other districts in Loudoun. This will destroy not only our view shed, our environment, the value of our properties and the quality of our lives, it will subject us to repeated eminent domain takings of easements across our properties to support expanding transmission infrastructure to power the data centers.
All of them support the transmission lines, you will see on their webpages letters they wrote in opposition to the prior siting of the MARL transmission line. But no letters opposed to the 500kV line itself or the proposed route and no letters opposing the 765kV line on V-Structure with guyed wires that we are also facing with the PJM project Valley Link!
The Piedmont Environmental Council and other so called historical and preservation groups in the area are also supporting the comprehensive plan amendments. Read their summer update letter here.
Loudoun County has already pitched the concept of amending the Comprehensive Plan with Transmission Corridors at the VA SCC during the Aspen/Golden case and using it as a pilot and was shot down!
The BOS actually proposed using a "standard accord review" of the comprehensive plan IN PLACE OF A VA SCC CPCN!
Pg1: "Q: Let me ask a factual question. If there is a feature shown on the comprehensive plan what does that mean for the approval of the project?
A: So as a feature shown, it would not have to go through the legislative process for review. ... All they would have to do is go through the normal site plan process to go ahead and identify the design they are proposing and because its a feature shown it's already approved at that level, so.. ."
Pg 3: "Q: So the question is does the County believe it has the authority to define and site the transmission corridor?
A: No ..."
Pg 6: "Q: And as part of that concept do you believe that a zoning change would be required to form a transmission corridor ?"
"Q: Is that a zoning change in your mind?
A: No, it is not"
Pg 16: "Q: Okay, So if we continue on 402, you want this application to stand in the place of a Certificate of Public Convenience and Necessity review at the SCC?
A: Correct .... again pre-designating certain areas where we would anticipate transmission corridors ...we do not have the state enabling legislation to do that.
Anyone with property in Loudoun County should take note and oppose this activity!
First Energy is naming the segment of the Mid-Atlantic Resiliency Link (MARL) that they propose to build from the Potomac River through Frederick County and Montgomery County Maryland the "Gore-Doubs-Goose Creek" 500kV transmission line. Word has it that the segment from Frederick County, Virginia, through Jefferson County, West Virginia and Loudoun County, Virginia and on across the Potomac will also be named the "Gore-Doubs-Goose Creek" 500kV transmission line.
First Energy has not scheduled or held any open houses in either Frederick or Loudoun Counties in Virginia or in Jefferson County, West Virginia. There was one and only one First Energy one open house in Maryland held in Frederick County, Maryland. When questioned about when they would be holding open houses in Virginia and West Virginia they would not divulge a date or how many open houses they would be holding. Property owners in Virginia and West Virginia are being intentionally kept in the dark .
A fact sheet from the Maryland open house stated "While the project is mainly using existing rights-of-way, there are “some limited areas” where the rights-of-way will have to be expanded to accommodate new transmission structures".
In a stunning display of cognitive dissonance the Loudoun County BOS has proposed to lower the property tax on data centers and data center personal property tax in particular. Lowering the data center tax rate is a "core element" of their financial plan.
The Loudoun County BOS' justification for lowering the rate is to "rein in the growth of government". They are pointing to the reduced rate for real estate taxes (you know the one where they lowered the tax rate and increased the land assessments that resulted in a larger overall tax bill than last year bill) and the pathetic decrease in personal property taxes on cars (that tax rate was reduced $.38 to $3.09 personal per $100 of the car's valuation.) If your car is worth between $5,000 and $10,000 that is a $14 to $28 annual savings in the "amount you lease the car you paid for" from the county. The county had a $280M surplus that could have been refunded to Loudoun County tax payers, but wasn't.
At the same the same time Loudoun County has appealed to the Virginia Supreme Court to push for under- grounding @3 miles of the Aspen-Golden 500kV line which would cost rate payers in the Dominion Zone an additional $480 million. Meanwhile western Loudoun is facing the loss of 365 acres of private property to host an additional 500kV plus a 765kV transmission line.
How about we charge the data centers more in taxes and impact fees to cover the destruction and loss of quality of life the infrastructure is causing? The data centers must PAY to underground the transmission lines (either HVAC or HVDC whichever is appropriate) being proposed to support their energy demands.
See Loudoun Now: Vol 10, No.36 July 17, 2025article "Rebalance: County Eyes Lower Data Center Taxes"
See Also Loudoun Now: July 10, 2025 "County Staff to Push for Lower Data Center Taxes to Balance Revenues"
And NetChoice: "Jaw-Dropping Numbers: Loudoun's Data Center Tax Revenue Could Top Real Estate Taxes In Just a Few Years"
In other data center news apparently PJM called upon Loudoun Counties data centers to run on their own backup generators to provide relief for the grid. Did you know there are 4000 backup generators in Loudoun County supporting the data centers?
See Loudoun Now: Vol 10, No.36 July 17, 2025article "Generator Use Jumps In Heat Wave; Turner pushes for Tier 4 Upgrades"
Date: Tuesday August 5, 2025
Time: 6:30pm
Location: University High School Auditorium
131 Bakers Ridge Road, Morgantown
Speakers:
West Virginian's against Transmission Injustice (WATI) is a new West Virginia nonprofit organization dedicated to advocating for the residents of Hampshire and Mineral Counties in West Virginia in opposition to the proposed transmission lines.
Hampshire County is impacted by both the MARL (500kV) and Valley Link (765kV) Transmission lines and Mineral County is impacted by MARL
WATI will have booths with information at the:
Dates: August 1-3, 2025
Location: Town of Romney, WV
Dates: August 1-3, 2025
Location: Mineral County Fairgrounds
Route 28
Fort Ashby, WV 26719
Visit them at https://www.wvatli.org subscribe for their newsletter and sign their petition
Thank you to everyone who wrote letters and / or signed the petition objecting to the incentive rates, these were uploaded to FERC (Docket ER25-1633 Valley Link Incentive Rates). Note that our Virginia Governor Youngkin sent comments in support.
Valley Link had requested a 10.9% return on equity plus an additional .5% for its new membership in PJM Interconnection, for a total interest rate of 11.4%. The project’s $3B cost will be slowly depreciated over perhaps four decades and during that time consumers would pay 11.4% on the remaining balance every year, making the final cost to ratepayers double or triple Valley Link’s actual cost to build.
The Construction Work In Progress (CWIP) in Ratebase incentive combined with the Hypothetical Capital Structure incentive will allow Valley Link to earn extra cash for its project before it is even constructed, all at consumer expense! Valley Link asked the Commission to make consumers “the bank” by loaning Valley Link money during the construction period and also requested that the Commission make consumers “the insurer of last resort” by granting the Abandoned Plant incentive that will charge consumers for Valley Link’s investment in the project even if it is never built! And the Valley Link Proposal had no cost caps! So they can come back every year and increase the cost of the project!
Although Chairman Christie dissented, FERC approved the incentive rates (Construction Work In Progress and Abandoned Plant Incentive) and the .5% for new membership in PJM. FERC set the ROE, formula rate, formula rate protocols and 60/40 Hypothetical Capital Structure incentive for hearing and settlement proceedings. I will be participating and post an update after settlement.
Chairman Christie's dissent stated "another major problem is that FERC’s general practice in granting transmission incentives has become a “check-the-box” exercise.
He continues "For example, I have stated that the Commission’s incentives policies—particularly the CWIP Incentive, which allows recovery of costs before a project has been put into service—run the risk of making consumers “the bank” for the transmission developer; but, unlike a real bank, which gets to charge interest for the money it loans, under our existing incentives policies the consumer not only effectively “loans” the money through the formula rates mechanism, but also pays the utility a profit, known as Return on Equity, or “ROE,” for the privilege of serving as the utility’s de facto lender. Further, just as the CWIP Incentive effectively makes consumers the bank for transmission developers, the Abandoned Plant Incentive effectively makes them the insurer of last resort as well. This incentive allows transmission developers to recover from consumers the costs of investments in projects that fail to materialize and thus do not benefit consumers. Just as consumers receive no interest for the money they effectively loan transmission developers through the CWIP Incentive, they receive no premiums for the insurance they provide through the Abandoned Plant Incentive if the project is never built. And if the CWIP Incentive is a de facto loan and the Abandoned Plant Incentive is de facto insurance—both provided by consumers—then the RTO participation adder, which increases the transmission owner’s ROE above the market cost of equity capital, is an involuntary gift from consumers. There has been and continues to be something really wrong with this picture."
If you have the time I highly recommend reading Chairman Christie's dissent
In 2009 During the PATH Case PJM Commissioned Black & Veatch to do an HVDC Study
There were two concepts. The most interesting one was Concept 2 - HVDC Underground
Concept 2 was to use HVDC Underground along the Mt Storm - Doubs line through Jefferson County, West VA and Loudoun County , VA and into Frederick , MD from Welton Springs to Kemptown, Maryland
Same location PJM has proposed to locate MARL (500kV) and Valley Link (765kV) through Jefferson County, West VA and the Lovettsville / Neersville Area in Loudoun County
It would have cost 2x the overhead 765kV option back in 2009, since these transmission lines are needed for the data centers , the data centers should be required to pay the difference between the HVAC overhead option and the HVDC Underground Option. Underground HVDC is much cheaper than underground HVAC . Underground HVAC cannot be used for long distances , HVDC can.
Also HVDC does not have the Electro-Magnetic Field (EMF) health issues that HVAC does
Recent studies by NextGen Highways indicate the price has come down significantly and the installation space is smaller now. There is no reason for pushing multiple massive 765kV and 500kV lines across thousands of acres of private property.
PJM needs to be required to do an HVDC study for its multi-state transmission lines
Loudoun County is in the process of creating a Comprehensive Plan Amendment on transmission corridors. The proposed amendments are from the Loudoun County Transportation and Land Use Committee and include adapting policies to encourage the "grouping of these tall structures within an existing and/or expanded transmission corridor right-of-way." Loudoun County has contracted with an engineering firm (Kimley-Horn) to map all the high voltage transmission lines in the county. This targets the property of every land owner along the existing HVAC transmission lines!!
Virginia is a Dillon Rule state which means a county has no authority except what the state has granted it. Loudoun County has no authority to site HVAC transmission lines or designate transmission corridors. Loudoun County also intends to add an overlay with the transmission lines on the county map. This will have serious implications for our property values and eventually the "By Right" use of our property !
This is a power grab and a land grab on the part of the Loudoun County BOS! It is essentially re-zoning our properties for energy infrastructure for the data centers and is setting us up for loosing our properties by successive Eminent Domain takings piece by piece!
Loudoun County BOS states "we don't have the authority to site the line the VA SCC does". The fact of the matter is they are doing this to influence / pre-empt the VA SCC to have their preferred route proposed in advance of the application submission / hearing.
The PJM Board Of Manager's new 765kV transmission line that was approved in spite of the obvious and unacceptable impacts to private property owners and significant impacts to national and state parks has a name - it is now the Valley Link Transmission line !
From Stop PATH West VA Blog:
Check back later ! More to come on how to comment and / or intervene at FERC in the Valley Link Transmission line incentive rate case!
As to electromagnetic fields (EMFs), the electric utility companies routinely say: nothing to see here. We disagree, particularly where multiple high voltage lines are sited on the same corridor.
Recent decisions by PJM have totally ignored and increased the health risks associated with EMF’s exposure from multiple high voltage lines on a single corridor. In August 2024, PLM approved a 500 kV line to be located in north west Loudoun County (Neersville/Lovettsville). In February 2025, PJM approved a 765 kV line for the same area, an area already burdened with a 500 kV line and a 138 kV line. Four total lines, two of which are 500kV plus the 765Kv, these are massive High Voltage Alternating Current (HVAC) on a corridor that may be as wide as 600 feet. The electromagnetic fields do not end at the edge of the right-of-way!
A world renowned expert on EMFs, Columbia University Professor Martin Blank (now deceased), and author of over 200 papers, submitted testimony before the SCC in the PATH litigation, Case No. PUE 2009-00043, in which he stated: “There can be no doubt that the proposed addition of the 765kV line to the existing 500kV line 138 kV lines would add to the level of EMF and thereby create additional potential risk.” Testimony at 15.
The risk of leukemia in children is real (Page. 3,6) as is “the risk to health of people in the vicinity” of the 765kV line. (Page 6). If these lines are built, a large swat of north west Loudoun will become hazardous to one’s health. Pictured chart is available here: https://emfcenter.com/what-distance-is-safe/
The PJM Board Of Managers has approved the 765kV transmission line in spite of the obvious and unacceptable impacts to private property owners and significant impacts to national and state parks.
If approved by West Virginia, Virginia and Maryland it will cross 216 miles on guyed-wire V-frame structures on a new 200' wide easement for its entire length. It will take at least 6,352 acres of land from rural property owners across 14 West Virginia counties, 3 Virginia counties and 1 Maryland county. It will impact 32 conservation easements plus the Monongahela National Forest, Appalachian National Scenic Trail, Chesapeake & Ohio Canal National Historical Park, Harpers Ferry National Historical Park,Potomac Heritage National Scenic Trail and it will run parallel down the view shed of the Potomac River.
For communities in Jefferson County, West Virginia and western Loudoun County, Virginia, Project 262 Proposal #708 would be a THIRD HVAC transmission line through their communities and across their farms and property: the existing 500kV, a new 500kV that has not been constructed with a 138kV under built plus a 765kV, 140' to 180' tall, guyed V-lattice structure beside it! In Loudoun, 365 acres would be taken from private property owners.
This is not a reliability problem this is new load / lack of generation problem driven by Loudoun County's unconstrained build out and expansion of data centers.
Virginia can build in-state energy generation for the data centers, the data centers can build their own energy generation on-site . Better yet the data centers can build closer to generation plants that have capacity .
There are 200 data centers built and 117 in the development pipeline. According to Supervisor Turner "There has not been a single day in 14 years when a data center was not under construction in Loudoun County We have more data centers than the next six U.S. markets combined. "
This is not an "accident", this is a direct result of the Loudoun County Board of Supervisors continuing to approve new data centers and data center expansion. Exemptions are approved in spite of existing zoning regulations and thus far they have also refused to fix the zoning that allows data centers "by right" under the guise of "office buildings" . Our Supervisors are not as interested in the "by right" usage of property by private property owners, who are their own constituents.
The Loudoun County BOS can fix the data center energy demand by NOT granting exemptions to zoning rules for the data centers, adding a rule constraining the energy use of land zoned for office building to the average energy use of office space . Loudoun County needs a through house cleaning every one of our board of supervisors needs to be replaced.
To really understand the extent of data center energy demand issue in Loudoun, I would recommend you read "Loudoun County Virginia Data Center Capital of the World "A strategy for a changing Paradigm" written by Supervisor Turner
The Virginia Joint Legislative Audit and Review Commission report on Data Centers was completed in 2024. It found that data centers’ power usage in Virginia is roughly equivalent to the electricity needs of 2 million Virginia households and is expected to double within 10 years. Within a 15 year timeframe the amount of energy that would need to be imported would increase by over 50% . This is not a sustainable situation.
NextERA has started working its routing study for its MARL segment through Green and Fayette counties in Pennsylvania, Preston, Monongalia, Mineral and Hampshire counties in West Virginia and Garrett and Allegany counties in Maryland
Highlights:
NextERA has a survey for its study area (See Alerts & Actions). Anyone can enter comments , you do not have to enter your name, contact information or any property information. Be sure to let NextERA know they are not fooling anyone. This transmission line is for unconstrained data center growth in Loudoun County.
Copyright © 2025 Stop MARL Virginia - All Rights Reserved.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.