Signed in as:
filler@godaddy.com
Signed in as:
filler@godaddy.com
The Loudoun County BOS , our Loudoun delegates , Waterford, Piedmont Environmental Council and LTLA have gotten PJM to propose an alternative to MARL. Its an additional 167.48M for PJM rate payers, on top of that it is still a greenfield line in Western Loudoun its just on someone else's property !!!
MARL Alternative was briefed at the July 9th PJM TEAC (pgs 40 - 45 : PJM Reliability Analysis Update – item 10, July 9,2024 . The MARL Alternative moves the transmission line from the green fields in rural mid-Western Loudoun County to the green fields in rural far Western Loudoun County parallel to the existing Mt.Storm - Doubs line, across the Potomac through green fields parallel to existing lines in Frederick County Maryland plus a brand new 2 mile pure green field corridor around Doubs which is Frederick / Montgomery Counties then another green field segment parallel the existing transmission lines through Montgomery County to the Doubs - Aspen Potomac crossing point . Miraculously enough Dominion Energy has somehow found a way to stack 3 500kv lines in the existing easement between the Potomac and the Aspen substation .
I attended the PJM TEAC telecon and asked: Will you (NextERA, FirstEnergy, PJM) be providing a legally binding contract, to property owners adjacent to or with existing transmission lines on their property, stating that no additional easements will be requested? Their answer was no, they will be taking an additional 75' to 100' or more depending by eminent domain from property owners along the existing lines.
There is an additional 2 mile segment in Maryland around the Doubs substation that will be an entirely new green field corridor.
DO NOT Let politicians or the Waterford Foundation, the Piedmont Environmental Council or LTLA gas-light you into thinking this line will be built "within the existing easements". There is no commitment or legally binding agreement from the energy company to build it "within existing easements" this is propaganda.
The MARL Transmission line will take a "greenfield" easement from every landowner / property it crosses no matter where it is routed - unless it is routed along existing highway easements.
I also asked: Did NextERA look at any other geographic areas apart from what was recommended by the Loudoun County BOS such as Highways?
For example Route 7 crosses from West VA to VA across the Appalachian Trail and directly into Data Center Alley - The Aspen – Golden line is being built on Route 7. The Appalachian trail crossing at route 7 is ugly and hazardous – the National Park Service would be may be agreeable to adding a transmission line in that easement if improvements such as a raised pedestrian bridge were added. There are also crossings of the Appalachian at Route 9 and Route 50. The answer was no other routes were looked at.
The recently published paper by Mike Turner, Loudoun County Supervisor for Aspen, Loudoun County Virginia Data Center Capital of the World "A strategy for a changing Paradigm" specifically states that Route 7 is a viable transmission route into "Data Center Alley"
Our elected politicians would rather have the property of their constituents along the Potomac as well as the properties of citizens living in 2 counties of a neighboring state taken by eminent domain, to support data centers they approved, rather than have a transmission line built along a commuter highway that already has transmission lines on it and directly accesses "Data Center Alley".
PJM's next reading of the scope change pushing into far Western Loudoun and Maryland will be at the PJM TEAC Tuesday August 6th, 1:00pm - 3:00pm
Submit your comments opposing the Mid-Atlantic NIETC! If the Mid-Atlantic NIETC is approved , this would allow the federal government to site the MARL Transmission line using federal eminent domain in the event the transmission line was denied by any of the states (Pennsylvania, Maryland, West Virginia and Virginia).
NextERA would not have submitted this project for an NIETC Corridor unless they intended to take private property by eminent domain.
PUR-2024-00032 ASPEN GOOSE CREEK GOLDEN Substations & 500-230 kV Lines
PUR-2024-00044 5 Substations + 230 kV Lines
Case Info and Documents can be accessed here:
https://scc.virginia.gov/DocketSearch#caseDetails/144984
Hearing Examiner's Ruling on Extension - schedule updates are on Page 6:
https://www.scc.virginia.gov/docketsearch/DOCS/7z%40x01!.PDF
1) The deadline for the filing of:
2) The public hearing scheduled for 10 a.m. on August 6, 2024, for the receipt of telephonic public witness testimony
3) The portion of the hearing originally scheduled to be heard on August 7, 2024, will now be heard at 10 a.m. on September 18, 2024. <-- Note: In Richmond
NextERA submitted the geographic area where MARL is being sited (most of Western Loudoun) to the DOE to request a NIETC Corridor (National Interest Electric Transmission Corridor) . If approved , this would allow the federal government to site the line using federal eminent domain in the event the transmission line was denied by the states (Pennsylvania, Maryland, West Virginia and Virginia).
NextERA would not have submitted this project for an NIETC Corridor unless they intended to take private property by eminent domain.
ASPEN GOOSE CREEK
Case Summary For Case Number : PUR-2024-00032
Case Name: Virginia Electric and Power Co
Caption: Virginia Electric & Power Company - For approval & certification electric transmission facilities: 500-230 kV Aspen Substation, 500 kV Aspen-Goose Creek Line #5002, 500 kV & 230 kV Aspen-Golden Lines #5001, et al.
Case Info and Documents can be accessed here:
https://scc.virginia.gov/DocketSearch#caseDetails/144984
Order for Notice And Hearing - schedule starts on Page 22:
https://www.scc.virginia.gov/docketsearch/DOCS/7ynf01!.PDF
PJM has approved over $5 billion in new transmission lines to support the projected 7,500 megawatts of new data centers in both Maryland and Northern Virginia as well as to compensate for the planned retirement of 11,000 MW of fossil fuel generation in its eastern region.
Many of the lines proposed to support the data centers traverse Loudoun County. The largest one is the NextEra Mid-Atlantic Resiliency Link (MARL).
Copyright © 2024 Stop MARL Virginia - All Rights Reserved.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.