Signed in as:
filler@godaddy.com
Signed in as:
filler@godaddy.com
High Voltage Direct Current (HVDC) transmission lines use direct current as opposed to the alternating current which is used by the HVAC transmission lines. HVDC is used for bulk transfer of electricity across long distances and for direct point to point applications. Recently, it has begun to be used for shorter distances. HVDC voltages are in the 100kV to 800 kV range.
In comparison to HVAC, HVDC is more efficient and has 30 - 50% less line losses over long distances than HVAC. HVDC transmission lines do not require substations like HVAC transmission systems do, instead an HVDC converter substation is needed at each end of the transmission line.
In a typical overhead transmission line installation, HVDC uses a narrower right of way and smaller towers. Additionally HVDC cable can be more easily buried than HVAC and can be installed under water.
When comparing costs between HVDC and HVAC a 2022 feasibility study done by NextGen Highways found that buried HVDC is cost competitive to HVAC. The DOE notes that " converter stations required for HVDC deployment are expensive, however, with a breakeven distance of approximately 37 miles for submarine lines and 124 miles for overhead lines "
Black & Veatch did a study, for the PATH 765kV transmission line, that proved HVDC underground was a feasible solution through our area. Although it was more expensive (at that time) . An added benefit is that HVDC lines do not emit EMFs.
• The full title of that study was : Black & Veatch, "PJM Interconnection Potomac-Appalachian Transmission Highline (PATH) Project, HVDC Conceptual Study, B&V Project No.164996, B&V File 42.2004 , FINAL November 17, 2009 This was entered into the record as part of the Virginia SCC Case PUE 2009-00043 Application of PATH Allegheny Virginia Transmission Corporation
• Concept 2 was to use HVDC Underground along the Jefferson County, WV through Loudoun County segment of the Mt Storm - Doubs line
• The PATH line was to be in the same location PJM has proposed to locate MARL (500kV) and Valley Link (765kV) through Jefferson County, West VA and Loudoun County , VA and into Frederick , MD
IS HVDC UNDERGROUND FEASIBLE FOR THE MARL / GORE-DOUBS GOOSE CREEK 500KV AND VALLEY LINK TRANSMISSION 765KV LINES?
THE SHORT ANSWER IS YES!
Black & Veatch did a study, for the PATH 765kV transmission line, that proved HVDC underground was a feasible solution through our area. Although it was more expensive (at that time) . An added benefit is that HVDC lines do not emit EMFs.
• The full title of that study was : Black & Veatch, "PJM Interconnection Potomac-Appalachian Transmission Highline (PATH) Project, HVDC Conceptual Study, B&V Project No.164996, B&V File 42.2004 , FINAL November 17, 2009 This was entered into the record as part of the Virginia SCC Case PUE 2009-00043 Application of PATH Allegheny Virginia Transmission Corporation
• Concept 2 was to use HVDC Underground along the Jefferson County, WV through Loudoun County segment of the Mt Storm - Doubs line
• The PATH line was to be in the same location PJM has proposed to locate MARL (500kV) and Valley Link (765kV) through Jefferson County, West VA and Loudoun County , VA and into Frederick , MD
• The HVDC with underground Concept 2 (~25 miles underground ) would have cost 2x the overhead HVAC 765kV option ($1, 767M vs $3,595M) The additional $1,828M amounts to an extra $73.12M per mile
• Recent studies by NextGen Highways indicate the price has come down significantly and the installation space is smaller now.
• The Aspen/Golden Underground alternative proposed by Loudoun County to put 3 miles underground would be an additional $480M over the cost of the overhead line. $160M extra per mile!
=> The HVDC underground solution proposed in 2009 costs less per mile that what the county proposed for the Aspen/Golden HVAC underground alternate route
=> Data Center impact fees and taxes can be used fund the additional cost of under grounding Loudoun County must set aside funds for this purpose . At this point many of these companies are worth hundreds of billions to trillions in market caps (Amazon reached a $2 Trillion Stock Value on June 27, 2024 ) . Their executives and boards are paid 100's of billions of dollars . There is more than enough money to cover the cost of using HVDC and under grounding these lines
=> FirstEnergy is now responsible for two massive transmission lines targeted through our communities (Valley Link and Gore-Doubs-Goose Creek). Its time to re-evaluate and look at ONE single solution - figure out how much power can be reasonable imported from est Virginia and build A SINGLE INCLUSIVE HVDC Underground solution to solve it.
DOE New England Clean Power Project Summary
ISO New England Consumer Liaison Group Presentation
Copyright © 2025 Stop MARL Virginia - All Rights Reserved.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.