• Home
  • Alerts & Actions
  • MARL (500kV)
  • Valley Link (765kV)
  • Alternatives
    • Underground HVDC
  • Landowner Resources
    • Virginia SCC
    • Loudoun County
  • More
    • FAQs
    • About
    • Subscribe
    • Contact Us
    • West Virginia
  • More
    • Home
    • Alerts & Actions
    • MARL (500kV)
    • Valley Link (765kV)
    • Alternatives
      • Underground HVDC
    • Landowner Resources
      • Virginia SCC
      • Loudoun County
    • More
      • FAQs
      • About
      • Subscribe
      • Contact Us
      • West Virginia
  • Sign In

  • My Account
  • Signed in as:

  • filler@godaddy.com


  • My Account
  • Sign out

Signed in as:

filler@godaddy.com

  • Home
  • Alerts & Actions
  • MARL (500kV)
  • Valley Link (765kV)
  • Alternatives
    • Underground HVDC
  • Landowner Resources
    • Virginia SCC
    • Loudoun County
  • More
    • FAQs
    • About
    • Subscribe
    • Contact Us
    • West Virginia

Account


  • My Account
  • Sign out


  • Sign In
  • My Account

High Voltage Direct Current

    2009 10/22 PJM TEAC PATH HVDC Study

    In 2009 During the PATH Case PJM Commissioned Black & Veatch to do an HVDC  Study which was finalized in November of 2009.  Concept 2 was to use  HVDC Underground along the Mt Storm - Doubs (same location PJM has proposed to locate MARL (500kV) and Valley Link (765kV)  through Jefferson County, West VA and Loudoun County , VA and into Frederick , MD  from Welton Springs to Doubs

    It would have cost 2x the overhead 765kV option but recent studies by NextGen Highways indicate the price has come down significantly and the installation space is smaller now.  

    PJM needs to be required to do an HVDC study for its multi-state transmission lines  

    There is no reason for pushing multiple massive 765kV and 500kV lines across thousands of acres of private property 

    PJM 10/22/2009 PATH HVDC Study

    Underground High Voltage Direct Current (HVDC)

    High Voltage Direct Current (HVDC) transmission lines use direct current  as opposed to the alternating current which is used by the HVAC transmission lines.  HVDC is used for bulk transfer of electricity across long distances and for direct point to point applications.  Recently,  it has begun to be used for shorter distances.  HVDC voltages are in the 100kV to 800 kV range.


    In comparison to HVAC,  HVDC is more efficient and has 30 - 50% less line losses over  long distances than HVAC. HVDC transmission lines do not require substations like HVAC transmission systems do, instead an HVDC  converter  substation is needed at each end of the transmission line.  


    In a typical overhead  transmission line installation, HVDC uses a narrower right of way and smaller towers. Additionally  HVDC cable can be more easily buried than HVAC and can be installed under water.


    When comparing costs between HVDC and HVAC a 2022 feasibility study done by NextGen Highways found that buried HVDC is cost competitive to HVAC.   The DOE notes that " converter stations required for HVDC deployment are expensive, however, with a breakeven distance of approximately 37 miles for submarine lines and 124 miles for overhead lines "

    References

    1. Comparison of HVDC vs HVAC
    2. Electric Technology:  Difference between HVAC and HVDC
    3. Detailed Differences Between HVAC and HVDC
    4. NextGen Highways Feasibility Study for Minnesota Department Of Transportation
    5. NextGen Highways  Buried HVDC is Cost Competitive
    6. DOE  Connecting the Country with HVDC

    HVDC Feasibility Studies and Papers

    NextGen Highways Feasibility Study for Minnesota Department Of Transportation (pdf)

    Download

    NextGen Highways Buried HVDC Is Cost Competitive (pdf)

    Download

    HVDC Transmission Lines In Progress / Completed

    Champlain Hudson Power Express

    Champlain Hudson Power Express

    Champlain Hudson Power Express

    • November,  2022 - Completion Date  2026 (Construction Progress) 
    • Canadian Border to Queens, New York 
    • 1,250 MW - enough power for more than 1 million homes
    • HVDC cable
    • 339 miles with 60% in waterways and 40% buried underground
    • "This project is entirely privately funded, and the overall cost is approximately $6 billion" (CHPE Q&A)

    Read More

    Neptune Transmission

    Champlain Hudson Power Express

    Champlain Hudson Power Express

    •  June 2005 - Completed June 2007 
    • New Jersey  To  Long Island, New York
    • 660 MW, enough power  for about 600,000 homes 
    •  500 kV  HVDC cable
    • 65 miles, @15 miles buried underground &@60 miles underwater
    • $650 Million, This project was privately funded.   (Neptune Project Development) 

     

     

    Read More

    The Hudson Project

    New England Clean Power Link

    New England Clean Power Link

    • May 2011 - Completed June 2013 
    • New Jersey , Long Island New York
    • 660 MW - enough power for about 600,00 homes
    •  345 kV HVDC cable
    • 7.5 miles, entirely underground & underwater. It follows existing railroad rights-of-way, through an inactive railroad tunnel to the edge of the Hudson River in Edgewater.  It is then buried beneath the Hudson for approximately three-and-a-half miles
    •  $850 Million

    Read More

    New England Clean Power Link

    New England Clean Power Link

    New England Clean Power Link

    •  In progress 2024  -  "The project has received all required permits that allow it to bury two  six-inch-wide cables an estimated 150 miles, all in Vermont. "
    • Canadian border to Vermont 
    • 1,000 MW
    •  300 kV  - 320 kV HVDC cable
    • 150 miles, all under water or  buried underground in existing rights-of-way
    •  $1.6 billion merchant line will be privately financed and will not use taxpayer dollars 

    Read More

    HVDC Transmission Lines Proposed

    Power the South Bay Project

    Power the South Bay Project

    Power the South Bay Project

    • Expected to start 2026  with a completion date in 2028 
    • California
    • 500 kV and 320 kV  HVDC cables + 230 kV HVAC
    • 4 miles 230 kV AC underground and overhead and 8 miles 320 kV underground and overhead



     

     

    Read More

    Power Santa Clara Project

    Power the South Bay Project

    Power the South Bay Project

    •  Expected to start 2026  with a completion date in 2028 
    • California
    •  500 kV and 320 kV HVDC cables
    • 1 mile 500 kV buried underground and 13 miles 320 kV buried underground


     

     

    Read More

    Copyright © 2025 Stop MARL Virginia - All Rights Reserved.

    • Home
    • Alerts & Actions
    • MARL (500kV)
    • Valley Link (765kV)
    • Neighbors
    • Subscribe
    • Contact Us
    • West Virginia

    Powered by

    This website uses cookies.

    We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

    Accept